Bids for the construction of the Outer Port at the Port of Gdynia have been opened
On 30 September 2026, the bids were opened in the procedure to select a private partner for the ‘Construction of the Outer Port at the Port of Gdynia’ project. One bid was received by the deadline, which brings the bid submission phase to a close and marks the start of the next stage of the procedure.

The following bidder submitted a bid in the tender procedure:
- Terminal Investment Limited Gdynia Sp. z o. o., ul. Jerzego Waszyngtona 13B 81-342 Gdynia
The bid will now be analysed and assessed in accordance with the criteria and rules laid down by law. The Port of Gdynia Authority S.A. has 90 days to complete this stage. A decision regarding the selection of a private partner will be made on the basis of the assessment results.
“The adopted formula of a multi-stage dialogue with potential partners has served its purpose. For many months, we have been working together on the key assumptions of this highly complex project. I would like to thank the participants in the procedure for their commitment and hard work, as well as the Port of Gdynia team, which led this demanding process. Today’s opening of bids marks the end of an important stage in the work on the Outer Port and allows us to take the next step towards its realisation,” says Piotr Gorzeński, Chairman of the Port of Gdynia Authority S.A.
Outer Port – a new space for the development of the Port of Gdynia
The Outer Port is one of the Port of Gdynia’s key development projects. It involves the construction, on reclaimed land, of a new pier extending out to sea, which will create additional space for the development of port operations. One of its main components will be a deep-water container terminal with a cargo handling capacity of at least 2.5 million TEU per year, designed to handle the largest ocean-going vessels calling at the Baltic Sea.
The project is being implemented as a public-private partnership (PPP). Under this model, the private partner is responsible for financing and constructing the terminal, and subsequently for its operation and maintenance for the period specified in the contract. The selection of a partner is being conducted through a competitive dialogue, which has enabled the Port of Gdynia Authoirty S.A. and the participants in the procedure to work together on detailed solutions and to divide of responsibilities within the project.
The procedure for selecting a private partner is one of the elements of the preparation for the Outer Port. At the same time, construction is underway on new protective breakwaters, which will create a safe port basin for the future port. Four sections of breakwaters with a total length of nearly 2.5 km are being built, utilising, among other things, massive reinforced concrete caissons. The first of these was towed into position and settled on the prepared foundation in July 2026. At the same time, plans are being drawn up for future road and rail access to the Outer Port.